Laytime is the period agreed in a voyage charter party during which the charterer may load or discharge cargo without paying the shipowner anything beyond the freight. If cargo operations take longer, the charterer pays demurrage. If they finish early, the shipowner may pay despatch.

This guide covers how laytime is expressed, when it starts and stops, the key terms such as SHINC, SHEX and WWD, and a worked calculation from a discharge at İskenderun.

What does laytime mean in shipping?

A ship earns money only while she trades. Every hour alongside a berth is an hour she is not carrying cargo. The shipowner accepts some port time as part of the freight, and laytime is how much of it.

The Laytime Definitions for Charter Parties 2013, published by BIMCO with CMI, FONASBA and the Baltic Exchange, define laytime as the agreed period during which the owner makes the ship available for loading or discharging without payment additional to the freight.

Laytime belongs to the voyage charter and the contract of affreightment (COA). Under a time charter, the charterer pays hire for every day of the charter, so port delay is already the charterer’s cost and laytime does not apply.

How is laytime expressed in a charter party?

The charter party fixes laytime in one of three ways:

  • Fixed period: a set number of days or hours, for example “4 days SHINC for loading”.
  • Cargo handling rate: laytime is calculated from the cargo quantity, for example “8,000 metric tonnes per weather working day”. A 50,000 mt cargo at that rate gives 6.25 days of laytime.
  • Customary quick despatch (CQD): no figure is agreed. The charterer must load or discharge as fast as is customary at that port. Disputes are more likely because the allowance is not a number.

The rate method is the most common in dry bulk trades. It ties laytime to the actual cargo size, which suits fixtures where the final quantity is only confirmed at the loading port.

When does laytime start?

Laytime does not start the moment the ship drops anchor. Three conditions normally have to be met.

  1. The ship is an arrived ship. Under a berth charter, she must be at the berth. Under a port charter, she must be within the port at a place where ships usually wait, at the immediate and effective disposition of the charterer. This is the test set by the House of Lords in The Johanna Oldendorff (1973).
  2. The ship is ready. Her holds are clean and dry for the cargo, her gear works, and she holds the documents and clearances needed to start cargo work. Timing matters too, under the LayCan window: a ship tendering NOR before laydays begin usually cannot start laytime early unless the charterer agrees.
  3. Notice of Readiness (NOR) is tendered. The master or the agent tells the charterer, shipper or receiver that the ship has arrived and is ready.

Most charter parties then add a short notice time before laytime starts. GENCON 1994, for example, starts laytime at 13:00 the same day when NOR is given up to and including 12:00, and at 06:00 the next working day when NOR is given after 12:00 during office hours.

Congested ports change the picture. Phrases such as WIBON (whether in berth or not) and WIPON (whether in port or not) let NOR be tendered while the ship is still waiting. They move the risk of waiting time from the shipowner to the charterer.

What stops laytime?

Once started, laytime runs continuously unless the charter party excludes a period. Typical exceptions are:

  • Weather: rain or swell that stops cargo work, where laytime is counted in weather working days. Rain is critical for grain, fertiliser and other cargoes that must stay dry.
  • Sundays and holidays: excluded under SHEX-type terms, but counted under SHINC.
  • Shifting: moving from the anchorage to the berth, or between berths, is often excluded.
  • Strikes and port stoppages: excluded only if the strike clause says so.
  • Ship’s fault: breakdown of the ship’s cranes or a delay caused by the crew does not count against the charterer.

At Turkish ports, the weekend is Saturday and Sunday. Public holidays include New Year’s Day, 23 April, 1 May, 19 May, 15 July, 30 August and 29 October, plus Ramazan Bayramı and Kurban Bayramı. The two religious holidays follow the lunar calendar and move about 11 days earlier each year, so they should be checked against the laydays before fixing on SHEX terms. In some Middle Eastern ports, Friday replaces Sunday as the rest day, and charters use FHEX instead.

What do the common laytime terms mean?

These abbreviations appear in almost every dry bulk recap. Each one changes which hours count against the charterer.

Laytime Terms Charter party abbreviations
Common laytime abbreviations and their effect on the laytime clock
Term Full form Effect on the clock
SHINC Sundays and Holidays Included Laytime counts every day, including Sundays and holidays
SHEX Sundays and Holidays Excepted Sundays and holidays do not count; Saturdays do
SATSHEX / SSHEX Saturdays, Sundays and Holidays Excepted Saturdays are excluded as well
FHEX Fridays and Holidays Excepted Used where Friday is the weekly rest day
WWD Weather Working Day Time when weather prevents cargo work is excluded
UU Unless Used Excepted periods count only if cargo work is actually done
EIU Even If Used Excepted periods never count, even if cargo work is done
WIBON Whether In Berth Or Not NOR may be tendered while waiting for a berth
WIPON Whether In Port Or Not NOR may be tendered before the ship enters the port
CQD Customary Quick Despatch No fixed laytime; work as fast as the port’s custom

When does laytime end?

In dry cargo trades, laytime ends when loading or discharging is completed. Some charter parties extend this to the completion of cargo documents or the disconnection of shore equipment. The exact moment is recorded in the Statement of Facts, because a difference of a few hours can change a demurrage claim.

How do laytime, demurrage and despatch connect?

Laytime is the allowance. Demurrage and despatch settle what happens when the allowance is exceeded or not used.

  • Demurrage is an agreed daily rate the charterer pays once laytime has expired. It works as liquidated damages: the shipowner does not need to prove an actual loss.
  • Despatch is an agreed rate the shipowner pays when operations finish before laytime runs out. It is often set at half the demurrage rate.

The principle “once on demurrage, always on demurrage” matters most here. After laytime expires, laytime exceptions such as Sundays or rain no longer stop the clock, unless the charter party expressly says they also apply to demurrage. The BIMCO 2013 definitions state the same rule.

What are reversible and averaged laytime?

When a voyage has one load port and one discharge port, the charterer may have an option on how the two allowances are combined.

  • Reversible laytime: loading and discharging time are added together into one pool. Time saved at the load port can be used at the discharge port.
  • Averaged laytime: separate calculations are made for loading and discharging, and the time saved in one is offset against the time on demurrage in the other.

Both options usually favour the charterer. Without them, laytime is non-reversible: each port has its own allowance, and despatch at one port does not cancel demurrage at the other.

How do you calculate laytime? A worked example

A Supramax bulk carrier discharges 50,000 mt of wheat at İskenderun under these terms:

  • Discharge rate: 8,000 mt per weather working day, SHEX
  • Laytime allowed: 50,000 ÷ 8,000 = 6.25 days = 150 hours
  • NOR: GENCON 1994 rules, tendered Tuesday 6 October 2026 at 10:30
  • Demurrage: USD 15,000 per day pro rata; despatch: USD 7,500 per day on laytime saved

NOR was tendered before 12:00, so laytime starts at 13:00 the same day.

Laytime Statement Worked example — İskenderun, October 2026
Day-by-day laytime statement for a 50,000 mt wheat discharge at İskenderun
Date (2026) Period Event Counted Running total
Tue 6 Oct 13:00–24:00 Laytime commences 11h 00m 11h 00m
Wed 7 Oct 00:00–24:00 Rain stops discharge 14:00–20:00 (6 h excluded) 18h 00m 29h 00m
Thu 8 Oct 00:00–24:00 Discharging 24h 00m 53h 00m
Fri 9 Oct 00:00–24:00 Discharging 24h 00m 77h 00m
Sat 10 Oct 00:00–24:00 Saturday counts under SHEX 24h 00m 101h 00m
Sun 11 Oct 00:00–24:00 Sunday excepted, no work 0h 00m 101h 00m
Mon 12 Oct 00:00–24:00 Discharging 24h 00m 125h 00m
Tue 13 Oct 00:00–24:00 Discharging 24h 00m 149h 00m
Wed 14 Oct 00:00–01:00 Laytime expires at 01:00 1h 00m 150h 00m

Outcome A, demurrage. Discharge is completed on Thursday 15 October at 13:00. The ship is on demurrage from Wednesday 01:00 to Thursday 13:00, which is 36 hours or 1.5 days. Demurrage due: 1.5 × USD 15,000 = USD 22,500. Any rain during those 36 hours still counts, because the ship is already on demurrage.

Outcome B, despatch. Discharge is completed on Monday 12 October at 13:00. Laytime used is 101 + 13 = 114 hours, so 36 hours (1.5 days) are saved. Despatch due: 1.5 × USD 7,500 = USD 11,250.

Real calculations carry many more lines: shifting, partial rain stoppages, hatch-by-hatch work, holidays falling inside the laydays. Our Online Laytime Calculator handles weather working days and partial counting, logs the full Statement of Facts line by line, and saves each calculation as a file you can reopen later. The single-port version works on an irreversible basis.

Why does the Statement of Facts decide the claim?

Every laytime calculation is built on the Statement of Facts. The SOF is the port agent’s chronological record of the ship’s stay: arrival, NOR tendered, berthing, start and end of cargo work, every stoppage and its cause, and completion.

As a port agent, Heisenberg Shipping prepares the SOF at Turkish ports and gets it signed by the master and the terminal or receiver. A stoppage logged as “rain” instead of “no cargo available” moves the cost from one party to the other. That is why an accurate, contemporaneous SOF is the strongest evidence in any laytime or demurrage claim.

Where a charterer or owner needs an independent record at a Turkish port, a protective agent can monitor the SOF on their behalf.

Laytime vs LayCan vs demurrage vs despatch

Side by Side Four terms, four different questions
Comparison of laycan, laytime, demurrage and despatch
Term What it is Who pays or benefits
LayCan The date window in which the ship must arrive and tender NOR Charterer may cancel if the ship misses the cancelling date
Laytime The time allowed for loading or discharging, included in freight Nobody pays while laytime runs
Demurrage Agreed daily rate once laytime has expired Charterer pays the shipowner
Despatch Agreed rate for laytime saved Shipowner pays the charterer

Frequently asked questions

What is the difference between laytime and laycan?

LayCan is the date range in which the ship must arrive at the loading port. Laytime is the time allowed for cargo work once she has arrived and NOR has taken effect. A ship can arrive within laycan and still wait before laytime starts.

Does laytime apply to time charters?

No. A time charterer pays hire for every day the ship is on charter, including port time. Laytime and demurrage are voyage charter and COA concepts.

What does “once on demurrage, always on demurrage” mean?

After laytime expires, the exceptions that stopped laytime, such as Sundays, holidays or rain, no longer stop the clock. Demurrage runs continuously unless the charter party expressly applies those exceptions to demurrage as well.

Who calculates laytime?

The shipowner or operator usually prepares the laytime statement after the voyage, using the Statement of Facts and the charter party terms. The charterer checks it and either accepts or disputes it.

What is the difference between SHINC and SHEX?

Under SHINC, laytime counts on Sundays and holidays. Under SHEX, Sundays and holidays are excluded, which makes the same cargo take more calendar days to use up the laytime.

Is there an online tool to calculate laytime?

Yes. Heisenberg Shipping’s Online Laytime Calculator is built for dry bulk laytime, demurrage and despatch calculations.

Managing laytime at Turkish ports

Laytime is short on paper and long in practice. The few words in a laytime clause decide whether a port delay costs the charterer, the shipowner or nobody.

If your ship is calling at İskenderun, Mersin, Aliağa or another Turkish port, our ship agency team keeps an accurate Statement of Facts from arrival to sailing. Contact us at agency@heisenbergshipping.com.

Sources: BIMCO, Laytime Definitions for Charter Parties 2013. This post is informational and does not constitute legal or commercial advice; always check the wording of your own charter party.

Discover Our Other Posts

Illustration of a geared bulk carrier with deck cranes under the title “What is Laytime in Shipping?”
Chartering

What is Laytime in Shipping?

Laytime is the clock that decides who pays for a ship’s time in port. Here…
A banner graphic featuring the bold text "Global Newbuilding Ship Orders in 2026" above a flat-style illustration of a large cargo vessel under construction in a shipyard block assembly line.
Chartering

Newbuilding Orders in H1 2026: A Supercycle Built on Fragile Ground

Owners ordered 1,481 vessels in the first six months of 2026. The volume is real;…
Side-profile illustration of a geared dry bulk carrier with the title "TPC in Shipping — What Tonnes Per Centimetre Means?"
Chartering

TPC in Shipping: What Tonnes Per Centimetre Means?

TPC (Tonnes Per Centimetre immersion) is the weight, in tonnes, that must be loaded or…
Illustration of a cargo ship representing ship registration, flag state, and maritime compliance for shipowners and operators.
Chartering

Ship Registration in Maritime Industry: Complete Guide for Shipowners and Operators

Ship Registration or Ship Registry is more than a flag on the stern. It is…